Gunn Highway Is Closed at the Pasco Line So It Won't Have to Close Longer Later

A 5-by-10-foot concrete box culvert sits under Gunn Highway near Lake Fern, carrying stormwater beneath the road at roughly 18830 Gunn Highway. Hillsborough County says it is "nearing the end of its service life." Since Thursday, Nov. 5, crews have had the road above it closed in both directions between Lutz Lake Fern Road and Tarpon Springs Road. They are taking out that box and putting in two 53-by-83-inch elliptical reinforced concrete pipes.

A week in, the detour is the part everyone feels. The county's own FAQ explains the reason for it. This closure is the planned, shorter version of something that could otherwise have come with no warning. The county ruled out a slower lane-by-lane job, ruled out waiting a year and paid extra to cut down the days. Every choice was made to keep the road from failing on its own schedule instead of the county's.

What's closed, and until when

The county's Nov. 2 release says the closure lasts up to four weeks from Nov. 5. Counted out, the latest end date falls in the first days of December. The county's project page puts it at "up to 28 days" and warns that inclement weather can cause delays. The county has given a maximum, not a promised reopening day.

Here's what holds while the barricades are up:

  • The closed segment: Gunn Highway between Lutz Lake Fern Road and Tarpon Springs Road, both directions.
  • The posted detour: Lutz Lake Fern Road, Dale Mabry Highway and Van Dyke Road.
  • The tolled alternate: the Veterans Expressway, with regular tolls.
  • Driveways: the contractor's traffic plan has to keep driveway and local property access open the whole time.
  • Utilities: the county says the work needs only minor utility adjustments, which generally don't call for scheduled outages.

The scale explains why this one gets talked about. According to Bay News 9's September report, county data shows about 20,000 vehicles a day travel through or near the work area. Most of those trips are people going between Hillsborough and Pasco, and the closure sits right on that seam.

Why the whole road, and not one lane at a time

The most common question about a road job like this is why it can't be done half at a time. The county says it considered that and dropped it:

"Due to the limited right-of-way and the presence of nearby utilities, it is not possible to safely complete the work while keeping any portion of the roadway open. Temporary lane closures were explored, but the constrained space made those options infeasible."

That answer comes from the FAQ added to the county's release. Gunn Highway here is a two-lane road with water on the landscape around it. The FAQ notes surface waters inside the project area and says silt fences, turbidity barriers and riprap stabilization are required to protect Lake Fern and the nearby waterways. Between the narrow right-of-way, the utility lines and the lake, there was no room left for a lane of traffic beside an open trench.

That leads to the bigger question of timing. If the road has to close completely, why now?

Why November, and why not "someday"

The county answered that in two parts.

The first part is summer. A summer closure would have missed the school-year traffic, and the county says it looked at that. It ruled it out because of contractor scheduling, lead times for materials and seasonal weather that raises the risk of delays. Permits, coordination and utility relocation also couldn't be finished in time for a summer start.

The second part is the one the whole project rests on. Asked what would happen if the work were pushed to future years, the county said the risk of the existing box culvert failing would rise, and that would "increase the duration and impact of road closure needed to replace the culvert as an un-planned emergency rather than as a planned project."

The planned version came with a public comment period, an open house, message boards along the detour and updated navigation apps. The county also says the road was safe to drive before construction and was routinely inspected to keep it in acceptable condition until work began. The point was to replace the culvert before inspections started turning up problems.

Here's how the planned version played out:

  1. Sept. 8 to Sept. 21: public comment window on the county's project page.
  2. Sept. 15: in-person open house at the Walker Middle Magnet School gymnasium, 8282 N. Mobley Road.
  3. Oct. 12: the original "on or after" start date for the closure.
  4. Nov. 5: the updated start, when the closure began.
  5. Early December: the outside edge of the 28-day window, weather permitting.

What the county paid to make it shorter

The cost lines show the same thinking. In August, the project page listed a cost estimate of $1,294,487. The November FAQ puts the total at $1,318,000. The county says that figure includes about $23,600 to expedite the work and shorten the road closure.

Against a project of more than $1.3 million, that's a small extra cost, spent entirely on days. It fits what county project manager Samir Ahmed told Bay News 9 in September, that crews hope to finish as quickly as possible. The 28 days is a ceiling the county has paid to come in under, not a target.

Living with the gap until the road reopens

The county's access requirement matters most to the businesses and homes on the closed stretch, because their driveways stay reachable even though through traffic can't pass. The county's FAQ answers whether businesses and residences remain accessible with a plain "Yes."

The Mutt Meetup at 18636 Gunn Highway is one of the places adjusting. Its website carries a traffic note about the Nov. 5 closure and says the business is staying open during construction. Owner Ever Lyons told Bay News 9, "Especially that first week, I think it's going to be a lot of confusion." She pointed to clients who drop their dogs off before long work shifts. The daycare's posted weekday hours run 7 a.m. to 6 p.m., and boarded dogs need to be dropped off by 4 p.m. on weekdays. Plan any detour around those times.

Keystone Bible Church, whose Odessa ministry center is at 10925 Tarpon Springs Road, has a Gunn Hwy Road Closure page for anyone who usually drives in on Gunn. It has four alternate route maps and suggests trying your route ahead of time, allowing extra time "especially during the first several days of the closure as traffic patterns adjust." Those maps are useful well beyond Sunday mornings. They're among the clearest drawings of the local workarounds anyone has published for this stretch.

Keystone Park & Recreation Center is at 17928 Gunn Highway. The county lists after-school and summer camps, classes, senior programs and athletic leagues there. A walkway connects it to the Austin Davis Public Library, which sits on the north side of the park with its own address at 17808 Wayne Road. For families heading to a program at either building, it helps to know the library has a Wayne Road address when you're mapping a route around the closure.

A few habits help in the meantime:

  • Trust the signs over memory. The county says navigation apps have the detour, and message boards along the route carry the details.
  • Price the toll against the time. For north-south trips, the Veterans Expressway is the alternate both the county and Bay News 9 point to, and regular tolls apply.
  • Call Public Works with questions. Hillsborough County Public Works Customer Service is at (813) 635-5400 or [email protected].

When Gunn Highway reopens, two elliptical concrete pipes will sit where the old box culvert was. The county says the new pipes will handle more drainage and last longer.

Detours like this one are part of everyday life near the county line, and I like keeping my neighbors up to date on them. If you're weighing how this Gunn Highway corridor connects to Pasco, or you're getting ready to sell a home off it and want to talk timing, reach out to Jenny Sells The Block Tampa. Let's chat, whether you're looking for a home or want to sell with confidence.